What the action involves

This action’s aim is to manage species rich floodplain meadows with:

  • appropriate conditions to allow natural seasonal flooding to occur. This means flooding that occurs without the use of control structures such as sluices and hatches to regulate water
  • a good cover of flowering grasses and wildflowers from late spring and during the summer months, including at least 1 frequently occurring and 3 occasionally occurring ‘indicator’ species typical of a species-rich floodplain meadow
  • suitable sward heights and structure for a species-rich floodplain meadow by autumn
  • enough flowering grasses and wildflowers left to go to seed to maintain or increase the presence and abundance of ‘indicator’ plant species typical of a species-rich floodplain meadow
  • appropriate scrub and rush cover for a species-rich floodplain meadow
  • any historic or archaeological features protected from damage

The purpose of this is to:

  • maintain or increase floodplain meadow habitats which support wildlife and biodiversity
  • provide valuable space for floodwaters
  • create potential for carbon capture and increased climate resilience
  • contribute to protecting valued landscapes and archaeology

You can use this action to manage:

  • existing floodplain meadows
  • floodplain meadows being restored or created

What you must do

Your Natural England adviser will assess your land. They’ll work with you to adapt and agree the activities you must do to achieve this action’s aim. All mandatory activities will be set out in your agreement document.

To get paid for this action, you must:

  • maintain, restore, or establish a mix of high value indicator plants typical of the floodplain meadow priority habitat – some indicator species will be frequent or occasional across the site, as set out in your agreement
  • maintain or restore the appropriate hydrology to allow flood water to flow naturally onto and off the field
  • maintain existing infrastructure including culverts, pipes, grips and ditches to allow floodwater to return to a watercourse
  • take an annual hay cut after 15 June (or a date agreed with your Natural England adviser), which must be field dried, turned or tedded, baled and removed – hay making may not be needed in the first years of a creation project
  • remove livestock for at least 8 continuous weeks during the spring and summer before taking the hay cut
  • graze the aftermath or take a second hay cut
  • manage injurious weeds and invasive non-native species by cutting, hand pulling and grazing, or using methods agreed with your Natural England adviser
  • protect historic and archaeological features

The advice you’re given by Natural England is specific to your land which means (where relevant) you may also need to:

  • restrict topping to areas and time periods in your agreement
  • control scrub, rushes and other competitive plant species to achieve the right vegetation conditions
  • remove livestock at certain times of the year outside of the shut-up period
  • maintain a continuous grass sward or vegetation cover over historic and archaeological features and prevent additional scrub encroachment on historic or archaeological features
  • establish additional plant species agreed with your Natural England adviser
  • carry out plant species surveys to monitor the habitat
  • take and record dipwell readings to monitor the site wetness
  • follow an agreed wildfowling strategy and record bag returns

You must not:

  • apply any inorganic fertilisers, digestate or other industrial by-product including paper waste – the application of organic fertiliser will be limited to 6 tonnes per hectare of farmyard manure but only in years when the land has not flooded in the previous winter
  • work on ditches between April and August – this may also apply to surface water features
  • plough, cultivate or reseed, unless this is part of an agreed sward creation and enhancement plan
  • supplementary feed except for the use of mineral blocks or other types of feed agreed with your adviser
  • take any actions to retain water on site artificially or to disconnect the site from its adjacent water course (unless agreed with your Natural England) adviser
  • harrow, roll or supplementary feed on historic or archaeological features
  • carry out mechanical operations or other activities that may cause significant disturbance to birds during the breeding season or the autumn and winter (this does not include ditch maintenance)
  • carry out land management activities in a way that causes poaching or overgrazing

When to do it

You must do this action each year of its duration.

Evidence to keep

You must keep evidence to show what you have done to complete this action. If it’s not clear that you have done this action in a way that could reasonably be expected to achieve its aim, the Rural Payments Agency (RPA) may ask for this evidence.

You must supply the evidence if they ask for it, including:

  • records of field operations
  • photographs
Eligibility, land types and admin detail

Where you can do it

You can do this action on eligible land that is all of the following:

  • located below the moorland line
  • in the floodplain (usually identified as flood zones 2 or 3 on the Environment Agency’s Flood map for planning
  • on land that naturally floods or that can be allowed to flood naturally

The land must also be one of the following:

  • permanent grassland that is existing lowland meadow priority habitat – it does not need to be mapped on the Priority Habitat Inventory
  • arable land, temporary grassland or permanent grassland that has a high or medium potential for restoration or creation of species rich floodplain meadows

If you’re restoring or creating a species rich floodplain meadow, you will need a restoration or creation plan. This could be done through either an implementation plan or feasibility study (as agreed with your Natural England adviser).

Your restoration or creation plan must include:

  • a map showing where restoration (from permanent grassland to grassland habitat) or creation (from arable or temporary grassland to grassland habitat) will take place
  • soil analysis results including the soil available phosphorus (Olsen P method) and the soil potassium status. Soil analysis must have been carried out within the last year.

Eligible land

You can do this action on land that’s :

  • an eligible land type
  • registered with an eligible land cover on your digital maps
  • declared with a land use code which is compatible with the eligible land cover

Available area

Total or part of the available area in the land parcel.

Rotational or static

This action is static. This means you must do it on the same location each year of the action’s duration.

Consents and permissions

To apply for this action, you’ll need:

  • to agree an implementation plan or feasibility study with your Natural England adviser if you’re restoring or creating floodplain meadows
  • Scheduled Monument Consent from Historic England for any work on scheduled monuments
  • consent from Natural England for any activity on land designated as a site of special scientific interest (SSSI)

You may need to:

  • obtain any necessary consents from the Environment Agency, Lead Local Flood Authority (LLFA) or Internal Drainage Board (IDB) before starting work involving hydrological features
  • get a wildlife licence from Natural England if your activities affect a protected species or their habitat
  • get advice from your Natural England adviser if you have other archaeological or historic features on land in your agreement

All archaeological and historic features (including scheduled monuments) are identified in your Historic Environment Farm Environment Record (HEFER).

If you’re a tenant, it’s your responsibility to check whether your tenancy agreement allows you to complete what’s required in the actions you choose. You may need your landlord’s consent.

Capital grants that support it

If you need to complete an implementation plan or a feasibility study before you apply, you can apply for capital grants plans funding.

You can also [apply for capital items] (https://www.gov.uk/government/collections/capital-items-guidance-for-applicants-and-agreement-holders) to help you achieve the action’s aims. Your Natural England adviser will discuss eligible capital items with you.

Read the full guidance on GOV.UK

What you can do on the same land

Actions and options you can put on the same area of a land parcel, by scheme.
SFI 2026
SFI 2023
CS Higher Tier, 2025+
CS options

OR1, OR2, OT1, OT2

Environmental Stewardship

N/A

SFI Shepherd
Planning around an existing agreement

See how Higher Tier interacts with your SFI plan, before you apply

SFI Shepherd builds an SFI26 application field by field from your RPA maps, and flags clashes with the Countryside Stewardship and SFI agreements a farm already holds. It tracks the 25% limited-area total that CSHT and SFI share across the whole holding, and exports a summary ready for the RPA portal.

Get your Soil, Manure and Nutrient Management Plans done today